Snag List for New Flat Handover: Inspection Checklist
How to prepare a snag list before taking possession of a new flat in Bengaluru: a room-by-room inspection checklist, tools to bring and your rights under RERA.
By the Homes in Bangalore editorial teamLast reviewed 6 min read1,265 words

Short answer
A snag list is a written list of defects, such as cracks, leaks, uneven tiles, faulty wiring or poor finishing, that you find when inspecting a new flat before handover and ask the builder to fix. Inspect room by room with water and power connected, photograph each issue, submit the list in writing and reinspect before you sign for possession. Defects found later can still be reported, because the RERA Act makes the builder responsible for them for five years from possession (verify).
Key takeaways
- ◆A snag list is a written record of defects in a new flat that the builder must fix, prepared before or at handover.
- ◆Inspect in daylight with water and power on, room by room, and photograph every defect with its location.
- ◆Submit the snag list in writing, get an acknowledgement and reinspect before signing an unconditional acceptance.
- ◆Under the RERA Act, defects you report within five years of possession must be fixed by the builder free of charge (verify).
When to prepare a snag list
The best time is after the builder sends the offer of possession and before you sign the possession letter. By then the flat should be complete, the occupancy certificate issued and utilities connected, so you can test everything as you would use it. Ask for an inspection appointment and allow enough time to check every room without rushing.
Take the agreement for sale, the specification annexure and the floor plan with you. Many snags are not poor workmanship but differences from what was promised: a different brand of fittings, a smaller balcony or a missing provision.
New flat inspection checklist, room by room
Use this checklist as a starting point and add items from your own specification list.
| Area | What to check |
|---|---|
| Walls and ceilings | Cracks, damp patches, uneven plaster, paint finish and gaps at joints |
| Floors and tiles | Hollow-sounding tiles (tap with a coin), chipped edges, uneven levels and gaps in grout |
| Doors and windows | Smooth opening and closing, locks, alignment, gaps, sealant around frames and glass condition |
| Plumbing | Water pressure in every tap, hot and cold supply, leaks under sinks, flushes and drainage speed |
| Bathrooms | Floor slope towards the drain, no pooling water, finish at corners and joints, exhaust fan |
| Electrical | Every switch and socket working, earthing, a labelled distribution board, breakers that trip correctly |
| Kitchen | Platform level and finish, sink outlet, and points for the purifier, chimney and appliances |
| Balconies and utility area | Slope and drainage, railing height and firmness, washing machine inlet and outlet |
| Fittings | Brands and models match the specification annexure |
| Measurements | Room sizes roughly match the floor plan; raise any major shortfall in carpet area |
| Your share of common areas | Allotted parking slot, meters, letterbox and access cards for your unit |
Tools to bring
A few simple tools make the inspection faster and the findings harder to dispute.
- A spirit level or a phone level app, for floors, platforms and frames
- A coin or small rubber mallet, for tapping tiles
- A socket tester or a phone charger, to check each socket
- A marble or small ball, to check the slope of bathroom and balcony floors
- A torch, measuring tape, masking tape and a marker, to light, measure and mark defects
- A bucket of water, to test drainage on bathroom and balcony floors
- Your phone camera, to photograph each defect with its location
How to record and submit a snag list
Record each snag with the room, the exact location, a short description and a photo reference, for example 'Master bathroom, floor near shower: water pools away from the drain'. Number every item so the builder can respond item by item, and separate serious issues, such as leaks, structural cracks or electrical faults, from cosmetic ones.
Send the list by email or letter to the builder's customer care or handover team and ask for a written acknowledgement and a date for rectification. After the work, reinspect against the same numbered list. If minor items remain when you take possession, attach the outstanding list to the possession letter or note it in writing, rather than signing a statement that the flat is free of defects.
Your rights after possession
Handover does not end the builder's responsibility. Under the RERA Act, if you report a structural defect or a defect in workmanship, quality or services within five years of the date of possession, the builder must fix it without charge, generally within 30 days, failing which you may be entitled to compensation (verify). Damage caused by your own alterations or misuse is a different matter.
Keep the possession letter, your snag lists and all correspondence, because the date of possession and the date you reported each defect both matter. If the builder does not respond, you can file a complaint with Karnataka RERA (opens official website).
Should you hire a professional inspector?
Independent engineers and inspection firms offer pre-handover inspections, sometimes with tools such as moisture meters and thermal cameras. They can be worth the fee if you lack time or experience, are buying from abroad, or the flat is large. Ask what the report includes, whether they reinspect after repairs and whether they have any link to the builder. If you live abroad, someone in Bengaluru can carry out the inspection and handover for you under a suitable authorisation.
How to carry out a snag inspection
- 1Book the inspectionAsk the builder for an inspection date after the offer of possession, with water and power connected.
- 2Prepare your documentsTake the agreement, specification annexure and floor plan, along with the tools listed above.
- 3Inspect room by roomWork through each room in daylight, testing every tap, switch, door and window.
- 4Photograph and number snagsRecord each defect with its location, a description and a photo.
- 5Submit the list in writingEmail the numbered snag list to the builder and ask for an acknowledgement and a timeline.
- 6Reinspect before possessionCheck each item against the list once the builder says it has been fixed.
- 7Record anything outstandingAttach pending items to the possession letter instead of signing an unconditional acceptance.
Frequently asked questions
What is a snag list?+
A snag list is a written record of defects and unfinished work found when inspecting a new flat, such as cracks, leaks, hollow tiles, faulty sockets or fittings that differ from the specification. You give it to the builder before or at handover and ask for each item to be fixed. Numbering the items and attaching photos makes follow-up much easier.
When should I do a snag inspection on a new flat?+
Do it after the builder offers possession and before you sign the possession letter, when the flat is finished and water and power are connected. That lets you test the plumbing and electrics properly. If the builder will not allow an inspection before handover, record defects in writing as soon as you receive the keys.
Can I refuse possession until the snags are fixed?+
It depends on the defects and your agreement. Minor cosmetic snags rarely justify refusing possession of a flat that has its occupancy certificate, and a refusal can be contested. A common approach is to accept possession with a written list of pending defects attached. For serious defects, take advice from an advocate before refusing.
Who fixes defects found after I move in?+
The builder, if you report the defect within five years of possession and it is a structural defect or a defect in workmanship, quality or services. Under the RERA Act, the builder must fix it free of charge, generally within 30 days (verify). Report defects in writing with photos, and approach Karnataka RERA if the builder does not act.
Sources