How to verify a project on Karnataka RERA
How to verify a project on Karnataka RERA before you book: registration, promoter details, approved plans, quarterly progress, complaints and buyer protections.
By the Homes in Bangalore editorial teamLast reviewed 5 min read1,016 words

Short answer
Open the Karnataka RERA portal, search for the project by name or registration number, and check that the promoter, land details, approved plan, and completion date match what you've been told. Also review the project's quarterly progress updates and any complaints.
Key takeaways
- ◆Search the Karnataka RERA portal by project name or registration number before paying any booking amount.
- ◆Confirm that the promoter name, land details, approved plan and completion date on the portal match the brochure and agreement.
- ◆Read the quarterly progress updates to see whether construction is keeping pace with the declared timeline.
- ◆Treat 'pre-launch' offers on projects not yet registered with Karnataka RERA as a red flag.
- ◆Check complaints and orders against both the project and the promoter's other projects.
What to check
- Registration number and validity period
- Promoter name matches the agreement
- Approved layout and building plans
- Declared completion date
- Quarterly progress reports
- Complaints and orders against the project or promoter
Red flags
- Bookings or 'pre-launch' offers before RERA registration
- Brochure specifications that differ from the approved plan
- Pressure to pay large amounts before an agreement is executed
What the RERA disclosures tell you
The portal holds far more than a registration number. Downloading the promoter's filings and comparing them line by line with the documents you've been given is the core of RERA verification.
Save copies of the filings on the day you book. Promoters update their records over time, and keeping the version that existed when you paid makes it easier to show what was promised if a dispute arises later.
| Disclosure on the portal | Compare it with | Why it matters |
|---|---|---|
| Promoter and landowner details | Names on the agreement and title deeds | A mismatch can reveal a joint development you weren't told about |
| Approved plans and number of units | Brochure and floor plan offered to you | Extra floors or units may not be approved |
| Carpet area of each unit type | Area stated in your agreement | RERA requires units to be sold on carpet area |
| Declared completion date | Possession date in your agreement | Delay compensation is measured against the agreed date |
| Designated project bank account | Account you're asked to pay into | Buyer payments should go to the project account |
| Quarterly progress updates | What you see on a site visit | Gaps suggest the schedule is slipping |
Buyer protections under the RERA Act
Knowing what the law requires of a promoter helps you spot agreement terms that don't follow it. Key protections include the following; have an advocate confirm how they apply to your agreement.
- No more than 10% of the cost taken as an advance before a registered agreement for sale
- 70% of amounts collected from buyers kept in a separate project account and used for land and construction costs
- No changes to the approved plans or common areas without the buyer consent the Act requires
- Structural defects reported within five years of possession to be rectified by the promoter
- Interest payable to buyers for delayed possession at the prescribed rate
- No transfer of the majority of the promoter's rights in the project without written consent from two-thirds of buyers and the authority's approval
- Common areas to be handed over to the association of buyers as the Act and the agreement require
Extended and lapsed registrations
Each RERA registration has a validity date. A promoter can apply for an extension, which Karnataka RERA (opens official website) may grant on grounds the Act allows, and the portal records it. A project running on an extended registration isn't automatically a bad buy, but it tells you the original timeline has already slipped.
If a registration has lapsed before completion, ask the promoter in writing for the extension order or the reason, and check whether Karnataka RERA has issued any directions on the project. Build the delay into your expectations for possession, rent you'll keep paying and any rental income you were counting on.
Frequently asked questions
Which projects must register with Karnataka RERA?+
Under the RERA Act, real estate projects generally must register if the land exceeds 500 square metres or the project has more than eight units or plots, including plotted developments (verify current thresholds). Projects that already had a completion or occupancy certificate when RERA came into force are typically exempt. If a project should be registered but isn't, the promoter cannot legally advertise or sell units in it.
Do real estate agents need to register with Karnataka RERA?+
Yes. Agents who sell or facilitate the sale of units in RERA-registered projects must register with Karnataka RERA and quote their registration number in dealings and advertisements. You can search an agent's name or number on the portal. A registered agent gives you a regulator to approach if something goes wrong, but you should still have your own advocate verify the title and approvals.
What can I do under RERA if a developer delays possession?+
If a promoter fails to hand over possession by the date in the agreement, the RERA Act generally lets the buyer either withdraw and get a refund with interest, or stay in the project and receive interest for every month of delay at the rate set by the rules. You can file a complaint on the Karnataka RERA portal. An advocate can advise which route suits your situation.
How do I file a complaint with Karnataka RERA?+
Complaints are filed online through the Karnataka RERA portal. You register as a user, select the project or agent, describe the grievance and upload supporting documents such as the agreement for sale and payment receipts. A fee applies (verify current amount). The authority issues notices to the promoter and holds hearings. For complex disputes or large sums, have an advocate draft and present the complaint.
Does RERA registration mean a project's title is clear?+
No. RERA registration means the promoter has disclosed land details, approvals and timelines to the regulator and accepted legal obligations. It does not certify that the title is free of disputes or that every approval is valid. Treat Karnataka RERA as one layer of due diligence, and still have an independent advocate review the title chain, encumbrance certificate and approvals before you commit.